When stripping an old floor, laying new tiles and repainting a flat, in what order is the work done?

First the old flooring is broken out and the rubble bagged and cleared, then wall preparation and floor tiling (including skirtings) are completed, and the final coats of paint go on last.

When renovating a studio or apartment that needs both a new tiled floor and a full repaint, doing the stages in the right sequence keeps the new finishes clean and undamaged.

Breaking up the old floor tiles and bagging the rubble

First, the old floor is broken out completely, the rubble is bagged up and cleared, and the bare slab is cleaned. All the heavy dust and wall knocks happen in this first phase.

Finished studio flat with new grey floor tiles and freshly painted walls

Next, the walls are prepared, the new floor tiles and tile skirtings are laid and grouted, and the final coats of wall paint are applied — here replacing dark blue walls with a bright, soft tone.

Jobs that show it

Small Flat with a New Floor and New Colours - After
Small Flat with a New Floor and New Colours - Before
BeforeAfter
Renovations

Small Flat with a New Floor and New Colours

The old floor was taken up and new tiles were laid, and the dark blue walls were repainted in a soft grey-green.

See the job step by step
Kitchen Renovation from Drawing to Finish
Renovations

Kitchen Renovation from Drawing to Finish

An old kitchen was stripped out completely and replaced with a new grey kitchen with an island, built to the design drawing.

See the job step by step

More answers

693 334 7282WhatsApp